Construction Progress – 29 MAR 2024

New Site Update

2 years had passed since this post. Time flies.

Beginning to see some foundation works in progress. The land is now clearly divided into 3 parcels.

Hard to imagine that this small piece of land is going to have 1,068 HDB units comprising of 2 room, 3 room and 4 room.

I wonder what will be built over the other 2 land parcels….Hmmm…

Nevertheless, it’s good to see things are happening and looking forward for the 1st level of precast units to be onsite!

Phases of BTO construction in Singapore

I asked AI the above question and this is what it gave me 🙂

  1. The duration of each phase in the construction of an HDB BTO project can vary based on factors such as the size and complexity of the project, availability of resources, regulatory requirements, and external factors like weather conditions. Here’s a rough estimate of the duration for each phase:

    1. Pre-Construction Phase:

      • Land Acquisition: Several months to a few years, depending on negotiations and legal processes.
      • Planning and Design: 6 months to 2 years, depending on the complexity of the project and regulatory approvals required.
      • Approval Process: 6 months to 1 year, depending on the efficiency of the approval authorities and the complexity of the project.
    2. Site Preparation Phase:

      • Clearing and Demolition: 1 to 3 months, depending on the size of existing structures and site conditions.
      • Earthworks: 1 to 3 months, depending on the extent of grading and earthmoving required.
    3. Foundation and Substructure Phase:

      • Piling and Foundation Works: 3 to 6 months, depending on soil conditions and the depth of foundations required.
      • Substructure Construction: 6 to 12 months, depending on the complexity and size of the building.
    4. Superstructure Construction Phase:

      • Building Construction: 12 to 24 months, depending on the number of floors and the construction method (e.g., conventional vs. prefabrication).
      • Installation of Utilities: Concurrent with building construction, typically 6 to 12 months.
    5. Facade and Interior Finishing Phase:

      • Facade Installation: 6 to 12 months, depending on the complexity of the facade design and availability of materials.
      • Interior Finishing: 6 to 12 months, depending on the number of units and the level of customization.
    6. Completion and Handover Phase:

      • Final Inspections: 1 to 3 months, depending on the thoroughness of inspections and any issues found.
      • Testing and Commissioning: 1 to 3 months, depending on the complexity of systems and any remedial work required.
      • Handover: Typically 1 to 2 months, depending on administrative processes and paperwork.

    It’s important to note that these timelines are approximate and can vary significantly based on project-specific factors. Delays can occur due to unforeseen circumstances such as labor shortages, supply chain disruptions, or changes in regulatory requirements. Therefore, it’s essential for project managers to continuously monitor progress and adapt schedules as needed to ensure timely completion.

Leave a Comment

Your email address will not be published. Required fields are marked *