Construction Progress – JUNE 2024

New Site Update – JUN 2024

Drove passed the site last weekend and saw the crane booms moving in the compound. So last minute decided to snap some picture of the progress.

Piling completed and now casting ground beam & 1st storey slab.
1st storey slab casting in progress
Blk 809A 2nd level Unit 143, 145, 137 & 139, Blk 808A Unit 117, 115, 133 & 135 are already up. From the shadows from the June's afternoon sun, some units facing AMK Ave 5 will not be a direct hit to the bedrooms and living of those units. The multi-storey carpark is also slowly taking shape.
Huge empty plots of land for future development. There is currently a bus-stop in from of the new BTO. Hope that that government will be building a covered link bridge to the bus-stop opposite. And let more buses ply through this route as there will be a lot more residents in this area in future.